OK y’all, I’m back.
Went up to the site today, and was told that because of all the rain,the ground is too sodden to pour concrete on, nevermind actuallypouring it IN the rain.
Also: the mesh has been removed becausethe curved bit of the wall -ride foundation moved as it was setting,causing it to be a bit out of line. So they are redoing it. Nae bother.
ATTENTION: please spread the word that going into the site andskating / biking on it is VERY UNCOOL. The shuttering for theconcrete (discussed in previous pages) is being damaged by people usingthem as ramps. THEY ARE THIN AND NOT BUILT FOR THAT.
WAIT UNTIL THE PARK IS DONE!!
THEMORE DAMAGE AND DISRUPTION CAUSED THE SITE, THE LONGER IT WILL TAKE TOCOMPLETE. THE LONGER IT TAKES TO COMPLETE, THE MORE CHANCE WE WILLSUFFER FROST DAMAGE AND HAVE TO WAIT UNTIL NEXT SPRING TO FINISH IT =IF THE COLD WEATHER SETS IN BEFORE THE POURING ISFINISHED!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
If it’s YOU: DON’T BE AN ARSE. YOU ARE MESSING IT UP FOR YOURSELF AND EVERYONE ELSE.
If you know that your pals are sneaking in, tell them NOT TO, and WHY.
As soon as the first transition goes in, there will be a night guard to keep watch.
Thanks, from everyone who actually wants this thing to get built.